04 · 90-day

CV

90-Day Rollout

04 / 10

Sep 1 – Nov 29

Foundation, production, delivery. Paper first, then records, then recon. 10–16 masters. New Jazz does not move.

Timeline

  1. Phase 1

    Foundation

    Sep 1 – Sep 30

    Paper, billing path, first Compound block. Lane locked before a session is billed.

  2. Phase 2

    Production

    Oct 1 – Oct 31

    Two tracking blocks, first Scale Fund draw, eight records at demo-or-better. Epic in the room for playback.

  3. Phase 3

    Delivery

    Nov 1 – Nov 29

    Mix close, 10–16 records delivered, billing recon, next 90-day drafted. No aesthetic drift.

Deliverables tracker

Countersign publishing + Scale Fund side letterFoundationCoveSep 5
Lock first Compound recording blockFoundationNile ParkSep 6
Ingest Lunchbox catalog into MW8FoundationHarper ValeSep 12
Align Epic/FakeBusy billing contactsFoundationJoey MarsalaSep 10
New Jazz lane brief (do / don't)FoundationCoveSep 8
Studio rate card + day-hold policyFoundationNile ParkSep 7
Kickoff — Lunchbox, MW8, CompoundFoundationCoveSep 8
Second Compound block (Oct 6–8)ProductionNile ParkOct 1
24 rows